| 1 |
Nailing & Fastening |
Structural Instability |
Check for "shiners" and irregular nail spacing in framing. |
| 2 |
Wet Room Thresholds |
Catastrophic Leaks |
Mandatory 24-hour flood test before any tile is laid. |
| 3 |
Service Penetrations |
Fire & Draft Risk |
Verify orange fire-rated foam in all wall/floor penetrations. |
| 4 |
Window Flashing |
Internal Mold |
Ensure "shingle-fashion" (overlap) layered installation. |
| 5 |
Duct Sealing & HVAC |
High Energy Bills |
Mastic seal on all HVAC joints; check for air leaks. |
| 6 |
External Cladding |
Facade Detachment |
Check for mechanical anchors vs simple adhesive. |
| 7 |
Concrete Curing |
Slab Cracking |
Wet-curing protocols; check for early shrinkage cracks. |
| 8 |
Electrical Rough-in |
Fire / Loose Wiring |
Verify secure junction boxes and stapled wires (every 4.5 ft). |
| 9 |
Insulation Continuity |
Cold Spots / Condensation |
Zero gaps in corners and around utility portals. |
| 10 |
Plumb & Level Walls |
Finish Quality Issues |
Check framing verticality before drywall closes. |
| 11 |
Floor Leveling |
Uneven Surface / Squeaks |
Laser-check slab leveling before hardwood/tile install. |
| 12 |
Roof Ventilation |
Shingle Overheating |
Verify ridge/soffit vents are clear of obstructions. |